HCM City to dredge polluted Nhieu Loc-Thi Nghe canal
01 March 2020 | 06:51:00 AM
A VND36.5 billion (USD1.58 million) project to dredge Nhieu Loc-Thi Nghe Canal in HCM City will be started later this week.
The project divided into three phases will be carried out from now to the year-end to deal with the 9-kilometre canal.
Nhieu Loc-Thi Nghe Canal
Around 122,000 cubic metres of mud is expected to be dredged said Pham Ngoc Dung, director of the Waterway Management Centre under the HCM CIty Department of Transport.
The project will clean around 1.4 kilometres of the canal each in the first and second phases. The remainder will be tackled in the third phase scheduled in the fourth quarter of this year.
The mud will be transported to Da Phuoc waste treatment area.
Dung added the city will use the technology of a Japanese company for controlling bad odours coming from the mud.
The canal was dredged eight years ago, but it continues to face severe pollution, causing mass fish deaths several times.
(dtinews.vn, NLD)
Views: 2035
Other news
Vietnam sees 11.3 per cent rise in new businesses over five months (11/06/2025 07:08:AM )
HCM City grapples with inflation as economic challenges mount (05/06/2025 06:39:AM )
Vietnam to export first batch of low-emission rice (04/06/2025 06:39:AM )
Hanoi summer fest blends tradition and tech (02/06/2025 06:50:AM )
Truong Hai Group proposes 61 billion USD investment in high-speed railway (28/05/2025 07:17:AM )
Illegal stalls dismantled on Thanh Hoa beach (22/05/2025 06:19:AM )
Vietnam eyes 8% growth in 2025 through strategic reforms (13/05/2025 05:43:AM )
Hanoi-Haiphong luxury train service to be operated this weekend (06/05/2025 07:03:AM )
Fuel prices increase after consecutive falls (25/04/2025 06:42:AM )